Dear Experts
I am trying to execute the MDVP collectively.
I entered one part number ( A) and it has the component B and 2 planned orders
Stock of component B is 200 pcs
Requirement from each planned order is 400 pcs.
so in total 800 pcs are needed.
But on doing Availability check, the system gives that 50% of each planned order can be produced.
Ideally only one planned order of 50% can be produced and not 2. But the system is showing otherwise and marks the component B as Missing component.
i am using firm planned order too...
I am using customized checking rule which checks only physical stock. and Partial confirmation.
Am I missing something. Kindly guide.
thanks and regards
Nagendra Kumar