Dear All,
I need to change the dates(basic start date and basic finish date) to a past date in a production order. Once I do this I'm getting the message 'Start date is in the past' as a warning. After I press enter for the warning , basic start date and end date is automatically sets to current date. I'm using backward scheduling type.
I'm getting this after the upgrade to newer SAP version. (SAP ECC 6.0; AFS 6.5) I didn't get this in previous version. (SAP ECC 5.0)
Please advise regarding this.
Regards
Jeewana