Hi,
Need some suggestion regarding short close of auto generated PR through network activities in project builder. We have maintained WBS, Network, Activity and material component in project builder and at the time of release of activity PR gets generated automatically with doc. type NB.
Suppose we have requirement of 10 quantity of Material X which we have maintained in CJ20N and PR generated for 10 quantities. We have placed an order for 8 quantities. Now our requirement is freeze and we want to short close remaining PR quantity.
So as per standard process, we should tick mark the close button in ME52N but the close button is in grey mode since the creation of PR.
So is it the standard process for auto generated PR? If it is the standard process then what is the solution for this case as the system consumes the budget for the remaining quantity.
With Regards,