Hello All
We executed CJCO (carry forward project budget) for one project.Even then do not see the balance of last fiscal year in current fiscal year in report S_ALR_87013558
It stills appears in previous year row and not in fical year 2014 in above report
Please see below
Lead column Budget Actual Commitment RemOrdPlan Assigned Available
Overall values 900.000 0 13.905 0 13.905 886.095
-------------------- -------------- -------------- -------------- -------------- -------------- --------------
Previous years 5.000 0 0 0 0 5.000
2014 895.000 0 13.905 0 13.905 881.095
The available balance in previous year 5.000 still appears in same year and not transferred to 2014
Could you any one of you have idea on this?
Your help and suggestions on this is highly appreciated
Thanks in Advance
Kumar